News
Major breaches were seen in pump station award to Tepui – -but procurement commission says unable to do anything as contract already signed

More than six months after a complaint was lodged by APNU+AFC MP David Patterson about a pump station contract award to Tepui Inc, the procurement commission found major breaches in the evaluation process but said it can do nothing about it as a contract has already been concluded.
The article Major breaches were seen in pump station award to Tepui appeared first on Stabroek News.