In 2018 eight of Region Six contractor’s winning bids were identical to engineer’s estimate – -collusion suspected
A special investigation by the Auditor General’s office on procurement procedures within the Region Six, East Berbice-Corentyne Regional Democratic Council revealed that the Region’s engineer during 2018 utilised information from a bidding contractor to prepare the Engineer’s Estimate.